Specifications
Table Of Contents
- Cover
- Table of Contents
- Part 1 General Information
- Part 2 Specifications
- Part 3 Refrigerant Circuit
- Part 4 Function
- Part 5 Test Operation
- Part 6 Troubleshooting
- Part 7 Appendix
- 1. Piping Diagrams
- 2. Wiring Diagrams for Reference
- 3. List of Electrical and Functional Parts
- 4. Option List
- 5. Piping Installation Point
- 6. Example of connection (R-410A Type)
- 7. Thermistor Resistance / Temperature Characteristics
- 8. Pressure Sensor
- 9. Method of Checking the Inverter’s Power Transistors and Diode Modules
- Part 8 Precautions for New Refrigerant (R-410A)
- Index
- Drawings & Flow Charts

Test Operation Si34-704
128 Test Operation
1. Test Operation
1.1 Installation Process
Below Figure shows the installation process. Install in the order of the steps shown.
3. Selection of Location
4. Inspecting and Handling the Unit
5. Placing the Unit
7. Field Wiring 6. Refrigerant Piping
8. Airtight Test and Vacuum Drying
9. Pipe Insulation
10. Checking of Device and Installation Conditions
11. Additional Refrigerant Charge and Check Operation
13. Test Run
Operations which require the
power to be turned on.