STEP 6
(Mounting The Offside Column)
1. Position the offside column at the designated chalk locations and secure to the floor following the
same procedures as outlined in STEP FIVE; Items 1-6.
STEP 7
(Mounting the Top Trough Assembly)
1. Remove all of the equalizer pulleys from the top trough assembly in preparation of installing it to the
top of the columns.
2. Using a lifting device, raise the top trough assembly into position on top of the columns. Bolt to the
columns using the 10 mm hex bolts, nuts and washers.
3. YOU MUST POSITION THE SWITCH ENCLOSURE ADJACENT TO THE POWERSIDE COLUMN. (See
figure 8)
NOTE: In order to route the equalizer cables the pulleys must be removed.
If the anchor bolts were loosened to aid on the installation of the top trough, tighten anchor bolts as indi-
cated in step 5 items 4 - 6.
Powerside column
Microswitch bracket
Fig: 8
WARNING