User guide

C3 User Guide
20
antenna at a greater height above the ground if required. Greater pole diameters
can be used if this is not a requirement.
Pre-cabling
It is prudent to consider the routing and protection of equipment cables prior to
installation. Cable is best protected above the ground by the use of rigid electrical
conduit (20 or 25 mm works best). This can also be used below ground in the
absence of specially designed direct-burial cable (see appendix A2 for more
information). If the rear entry cable options are being used cabling must be laid
prior to the installation of the mounting post, extended up and through holes drill in
the post (via the pilot marks provided on the mounting bracket), please see cable
routing option 2 below for instructions.
Unpacking
The C3 packing box is designed such that the parts required are unpacked in the
order as needed. It is not necessary to unpack the box completely beforehand.
This helps prevent parts being lost, damaged or soiled during installation.
C3 Solar Enclosure installation
Mounting bracket
Mounting option 1: Pole mount
Remove top packaging insert
Identify mounting bracket and hose-clamps
15-20mm
Figure 6. Ideal hose-clamp length