SURFACE PREPARATION
Surface preparation is key. The entire surface must be flat, structurally sound, dry, and stable. The
surface should be clean and free of dust, dirt, oil grease, paint, curing agents, sealers, loosely
bonded toppings, loose particles, old adhesive residues, and any other substance or condition
that may prevent or reduce adhesion.
Acclimate material a minimum of 24 - 48 hours prior to installation in the environment where it
will be installed.
Scrape or remove any contaminants, substance or condition that may prevent or reduce
adhesion. Some substances may require mechanical grinding for removal.
Sand or grind down all areas as needed. All surfaces must be smooth and flat, or imperfections
may show-through.
Install any metal flashing or trim that is required for the installation such as a metal drip edge
around the outside perimeter of a deck.
Fill in all depressions, joints, gaps, or damaged areas as needed with a latex cement-based
patching compound and sand smooth once it has “thoroughly” dried.
Sweep and thoroughly vacuum.
Seal all patched areas, pitch pockets, pitch streaks, red chalk, wood knots construction adhesive,
wood filler, etc. with an appropriate primer. Follow manufacturer’s directions for proper
application and mixing.
Suggestion: Zinsser Bin Shellac Based Primer Sealer
Do a final inspection to ensure the surface area is suitable and ready for the application of the
Dec-Tec DIY
IMPORTANT: Thoroughly inspect all material for visible blemishes or defects before starting the
installation. Installation of defective material will be regarded as acceptance of its condition
regardless of the defect and will void the product warranty.
INSTALLATION
LAYOUT
Plan your layout to avoid an unbalanced installation. As a rule of thumb, material should run
lengthwise and parallel to the most dominant wall to achieve the best appearance.
Make sure the surface area is square before laying out the material. Measure the diagonals from
all four corners. Take a tape measure and measure the distance from one corner to its diagonal,
and then measure the diagonal between the remaining two corners. If the measurements equal
one another, your surface area is square. If the measurements are different, you can make
adjustments with the first panel during the dry-fit. That's all there is to it!
If installing on an exterior deck, it is recommended to start from the outside edge of the deck
surface and work towards the building.
DRYFIT
Measure in 73" from outside edge when using 74” wide product or 36" from outside edge when
using 37” wide product and snap a chalk line. This will provide for a 1" overhang over the outside