Technical data
46
MCR 24, 24/28 MI, 30/35 MI, 34/39 MI 08/06/06-300008460-001-B
Maintenance
MCR boilers require little maintenance. An annual inspection is
compulsory.
Maintenance operations must be done by a qualified
professional.
If, on annual inspection, the combusted gas analysis is not in
compliance, a setting combustion operation must be carried
out.
If the ionisation current is less than 3, check the ignition/
ionisation electrode as well as the ignition line and the earth
connection.
Only original spare parts must be used.
1Inspection
Cut the power supply to the boiler.
Cut the gas supply to the boiler.
1.1 Checking the hydraulic pressure
Minimum pressure: 1 mbar. Add water to the installation if necessary.
Carry out a visual check for the presence of any water leaks.