Installation Guide
Table Of Contents
- Dell EMC PowerSwitch N3200-ON Series Installation Guide
- About this guide
- N3200-ON Series switch
- Site preparations
- N3200-ON Series switch installation
- Unpack
- Rack or cabinet hardware installation
- Ground cable
- Desktop
- N3208PX-ON ceiling-mount switch installation
- N3208PX-ON wall-mount switch installation
- Standard bracket two-post installation
- Two-post five-inch-offset switch installation
- Two-post flush-mount switch installation
- Wall- or ceiling-mount switch installation
- One RU ReadyRails installation
- Optics installation
- Switch start-up
- After switch placement
- Switch replacement
- External power adapter
- Power adapter holder assembly
- Wall or ceiling installation
- DIN rail installation
- Single-EPA and switch four-post installation
- Single-EPA and switch two-post center-mount installation
- Single-EPA and switch two-post front-mount installation
- Dual-EPAs two-post front-mount installation
- Dual-EPAs two-post center-mount installation
- Power supply
- Fans
- Management ports
- Installation using ONIE
- Specifications
- Dell EMC support
The ground lug ships with the optionally ordered DC version PSUs. The AC-no-OS version of the N3248PXE-ON switch, which
you must special order, also ships with the ground lug.
CAUTION: Grounding conductors
must
be made of copper. Do not use aluminum conductors.
NOTE: Coat the one-hole lug with an antioxidant compound before crimping. Also, bring any unplated mating surfaces to a
shiny finish and coat with an antioxidant before mating. Plated mating surfaces must be clean and free from contamination.
NOTE: The rack installation ears are not suitable for grounding.
To connect the ground cable to the switch:
1. Cut your user-supplied ground cable to the wanted length.
The cable length must facilitate proper operation of the fault interrupt circuits. Use the shortest cable route allowable.
2. Crimp the ground cable inside the ground lug.
3. Attach the other end of the ground cable to a suitable ground point such as the rack or cabinet.
The rack installation ears are not a suitable grounding point.
Desktop
One mounting option is to place the N3200-ON Series switch on a desktop.
The mounting supplies for this installation ship with the switch.
1. Locate the four rubber feet shipped with the switch.
2. Remove the paper backing on the bottom of one of the rubber feet.
3. Adhere the rubber foot to one of the four round position marks on the underside of the switch.
4. Repeat the process for the remaining three rubber feet.
5. Turn the switch over and place on a desktop.
N3208PX-ON ceiling-mount switch installation
This switch installation procedure applies to the compact N3208PX-ON switch only.
NOTE: Do not use this installation procedure for the full-width N3200-ON Series switches.
The mounting supplies for this installation ship with the switch. To complete this installation, you need a pencil, drill, and Phillips-
head drill bit.
26
N3200-ON Series switch installation