Installation Guide
Table Of Contents
- Dell EMC PowerSwitch N3200-ON Series Installation Guide
- About this guide
- N3200-ON Series switch
- Site preparations
- N3200-ON Series switch installation
- Unpack
- Rack or cabinet hardware installation
- Ground cable
- Desktop
- N3208PX-ON ceiling-mount switch installation
- N3208PX-ON wall-mount switch installation
- Standard bracket two-post installation
- Two-post five-inch-offset switch installation
- Two-post flush-mount switch installation
- Wall- or ceiling-mount switch installation
- One RU ReadyRails installation
- Optics installation
- Switch start-up
- After switch placement
- Switch replacement
- External power adapter
- Power adapter holder assembly
- Wall or ceiling installation
- DIN rail installation
- Single-EPA and switch four-post installation
- Single-EPA and switch two-post center-mount installation
- Single-EPA and switch two-post front-mount installation
- Dual-EPAs two-post front-mount installation
- Dual-EPAs two-post center-mount installation
- Power supply
- Fans
- Management ports
- Installation using ONIE
- Specifications
- Dell EMC support
2. Align the two mushroom heads on the switch with the two holes on the power adapter holder. Slide the power adapter
holder forward to lock it in place.
3. Use two screws to secure the power adapter holder to the side of the switch.
4. Install the AC power cable to the EPA and secure with the wire clip.
5. Bend the AC power cable 180 degrees along the holder wall and through the cable cutout.
6. Align the L-bracket with mushroom head on the switch and the power adapter holder.
Face the L-bracket flange towards the rear of the assembly.
7. Secure the L-brackets to the switch and the power adapter holder using four screws on each side.
8. Install the L-bracket to the two-post rack, and secure it with the rack-mounting screws.