Administrator Guide

To repeat the replication over a set amount of time, select Repeat Interval, then select how often to start replication and the
start and end times.
14. From the Replica Settings field, type the maximum number of replications the schedule can initiate.
Schedule a Replication to Run Once
Create a schedule for one replication to replicate the volume at a future date and time.
Steps
1. Click the Storage view.
2. In the Storage pane, select a PS Series group.
3. Click the Storage tab.
4. From the Storage tab navigation pane, select a volume.
The volume must be the source of a replication relationship.
5. Click Create Schedule.
The Create Schedule dialog box opens.
6. Click the Enable Schedule checkbox.
7. In the Name field, type a name for the schedule.
8. From the Frequency drop-down menu, select Run Once.
9. From the Date field, select the start date of the replication.
10. In the Time field, specify the start time of the replication.
11. From the Replica Settings field, type the maximum number of replications the schedule can initiate.
Edit a Replication Schedule
After creating a replication schedule, edit it to change how often the schedule initiates replications.
Steps
1. Click the Storage view.
2. In the Storage pane, select a PS Group.
3. Click the Storage tab.
4. From the Storage tab navigation pane, select a volume.
The volume must be the source of a replication relationship.
5. From the Schedules tab, select the replication schedule to edit.
6. Click Edit.
The Edit Schedule dialog box appears.
7. Modify the schedule settings as needed.
NOTE: For more information on the schedule settings, click Help.
8. Click OK.
Enable or Disable a Replication Schedule
After creating a replication schedule, enable or disable the schedule to allow the schedule to initiate replications or prevent the schedule
from initiating replications.
Steps
1. Click the Storage view.
2. In the Storage pane, select a PS Group.
3. Click the Storage tab.
4. From the Storage tab navigation pane, select a volume.
The volume must be the source of a replication relationship.
5. From the Schedules tab, select the replication schedule to enable or disable.
6. Click Edit.
The Edit Schedule dialog box appears.
Storage Center Replications and Live Volumes
491