Install Guide

Site preparations
The Edge 510 LTE platform connects the service provider edge or small-to-medium branch locations.
Use the platform on a desktop or optionally install the platform in a wall or rack.
NOTE: If you optionally install the platform into a rack or cabinet, install the platform first, and then install any additional
components such as cables or optics.
Topics:
Site selection
Platform mounting
Fans and airflow
Power connection
Storing components
Site selection
Ensure that the area where you install your platform meets the following safety requirements:
Near an adequate power source
Connected to a properly grounded power outlet
WARNING:
Earth the Edge 510 LTE. Connect the Edge 510 LTE to an outlet that is a properly wired, earth-
ground socket outlet.
Environmentalplatform locationcontinuous temperature range is 0°C to 40°C (32°F to 104°F)
Operating humidity:
5% to 85% (RH), noncondensing continuously
5% to 90% (RH), noncondensing Short term (< 1% of operational hour per year)
In a dry, clean, well-ventilated, and temperature-controlled room, away from heat sources such as hot air vents or direct
sunlight
Away from sources of severe electromagnetic noise
For more information about platform storage and environment temperatures, see Specifications.
Platform mounting
The Edge 510 LTE supports the following mounting options:
Desktop placement using rubber feet
Wall-mounting using wall mount brackets
Rack-mounting using the optional rackmount tray
Rack and platform ground
Ensure that you install in the platform in a grounded rack. Ground the rack to the same ground point the power service in your
area uses. The ground path must be permanent.
3
Site preparations 9