Install Guide

Table Of Contents
One RU ReadyRails installation
Install the N2200-ON Series switch using one of the following installation instructions. You can install the ReadyRails system
using the 1U tool-less square-hole method or one of three possible 1U threaded round-hole methods. The tooled installation
methods include two-post flush mount, two-post center mount, or four-post threaded mount.
NOTE: You must order the ReadyRails mounting supplies for this installation separately.
To begin installation, separate each rail assembly by sliding the inside rail out of the outside rail.
NOTE: For more installation instructions, see the installation labels attached to the rail assembly.
Figure 2. Separate rails
1U Tool-less mount ReadyRail installation
NOTE: For more installation instructions, see the installation labels attached to the rail assembly.
1. Face the ReadyRails flange ears facing outward. Place one rail between the left and right vertical posts. Align and seat the
back flange rail pegs in the back vertical post flange.
The center extractions show how the pegs appear in both the square and nonthreaded round holes.
N2200-ON Series switch installation
27