Deployment Guide

36 VCF on VxRail Multirack Deployment using BGP EVPN
sfo01-Leaf01A(config)# ip prefix-list spine-leaf seq 70 permit
172.25.101.0/24
sfo01-Leaf01A(config)# ip prefix-list spine-leaf seq 70 permit
172.25.102.0/24
sfo01-Leaf01A(config)# ip prefix-list spine-leaf seq 90 permit
172.16.49.0/24
7. Repeat the steps using the appropriate values from 5.8, for the remaining leaf switches.
Note: If any of the workload subnets need to have access to the underlay network, additional IP prefix lists
will need to be added.
6.3 Configure spine switches
This section covers the configuration of the Z9264-ON switch with the hostname sfo01-spine01 that is
shown in Figure 19.
Note: All switch configuration commands are provided in the file attachments. See Section 1.7 for instructions
on accessing the attachments.
AS 65100
Layer 3 connectivity to Leaf switches
Spine Switch
sfo01-Spine01
1/1/11 1/1/12 1/1/13 1/1/14
Spine Switch 2
sfo01-Spine02
1/1/11 1/1/12 1/1/13 1/1/14
192.168.1.0
192.168.1.2
192.168.1.4
192.168.1.6
192.168.2.0
192.168.2.2
192.168.2.4
192.168.2.6
Spine layer diagram
Note: Some of the steps in this section may already be done if all configuration steps from the VCF on VxRail
multirack deploying using BGP EVPN deployment guide were followed. All steps are included here to ensure
completion.
1. Configure general switch settings, including OOB management and NTP source.
OS10# configure terminal
OS10(config)# interface mgmt 1/1/1
OS10(conf-if-ma-1/1/1)# no ip address dhcp
OS10(conf-if-ma-1/1/1)# ip address 100.67.198.36/24