Setup Guide

Figure 6. Four-post threaded installation
2 For each rail, attach the front and back anges to the post anges with two user-supplied screws at each end.
S4100-ON Series system installation
You can mount the system in the 1U front-rack two-post, ush, or center conguration or a four-post conguration. The following is an
example of a front-rack conguration:
For the 1U two-post congurations, slide the system into the rails in the same manner as the four-post congurations.
1U front-rack installation
Congure the rails that are attached to the system.
1
NOTE
: For more information, see the installation instruction labels on the rail.
Attach the inner switch rails to the S4100–ON Series switch.
Line up the rail with the mounting heads and attach the rail to the chassis. Slide the rail back until it locks into place. The following
shows the detail of the front stando with the locking tab:
S4100–ON Series installation
15