Administrator Guide
• A recommendation about whether the destination volume is currently synchronized with the source volume is displayed
below the Sync Data Status eld in green or yellow text.
NOTE: For high consistency mode synchronous replications that are current, the Use Active Snapshot check box is
automatically selected.
Figure 73. Test Activate Disaster Recovery Dialog Box
b Select the server to which the test-activated volume will be mapped by clicking Change next to the Server label.
c Modify the remaining settings for the test-activated volume as needed, then click OK. These attributes are described in the
online help.
6 When you are done, click Finish.
• Storage Manager creates test-activated view volumes and maps them to the congured server(s).
• Use the Recovery Progress tab to monitor DR test-activation
Test DR Activation for a Single Restore Point
To test DR activation for a replication, use the corresponding restore point.
Prerequisites
• The restore point must be associated with a replication. Live Volume restore points cannot be tested.
• The destination volume must be present on the remote Storage Center. If the destination volume for a replication restore point is
missing, it cannot be tested.
• A server must be present at the DR site to perform test-activation.
Steps
1 Click the Replications & Live Volumes view.
2 Click the Restore Points tab.
3 Right-click the restore point, then select Test Activate Disaster Recovery. The Test Activate Disaster Recovery dialog box appears.
If the restore point corresponds to a synchronous replication, the dialog box displays additional information about the state of the
replication:
• The Sync Data Status eld displays the synchronization status for the replication at the time the restore point was validated.
• A recommendation about whether the destination volume is currently synchronized with the source volume is displayed below the
Sync Data Status eld in green or yellow text.
574