Preparing for Deployment
Before starting the Storage Center deployment, review the IPv address information below, cable and power on the system, and collect the
required information.
IPv Addresses
The configuration process uses DHCP to obtain IPv4 and IPv6 addresses from the data center network.
If DHCP is not available:
Configure the IPv4 address on the system running the Storage Manager client on the target subnet, and
Enable IPv6 addressing.
This allows the discovery and initial configuration to occur over the IPv6 link local address and then transition to the IPv4 address when
the controller IP addresses are configured.
If IPv6 is not allowed or is blocked, configure the Storage Manager client's NIC with two IPv4 IP addresses:
One IPv4 address configured on the target subnet
A second IPv4 address on the link local subnet, such as 169.254.10.10
This allows the discovery and initial configuration to occur over the IPv4 link local address and then transition to the IPv4 address when
the controller IP addresses are configured.
Connect Power Cables and Turn On the Storage System
Connect power cables to the storage system components and turn on the hardware.
About this task
If the storage system is installed without expansion enclosures, connect power cables to the storage system chassis and turn on the
storage system.
If the storage system is installed with expansion enclosures, connect power cables to the expansion enclosure chassis. Make sure you
power on each
expansion enclosure before turning on the storage system.
NOTE:
When powering on expansion enclosures with spinning hard drives, wait approximately three minutes for the
drives to spin up before powering on the storage system.
Steps
1. Make sure that the power switches are in the OFF position before connecting the power cables.
2. Connect the power cables securely to both power supply/cooling fan modules in the storage system chassis.
5