User's Manual
Table Of Contents
- Safety Precautions
 - About This Manual
 - Table of Contents
 - Chapter 1 Introduction
 - Chapter 2 System Description
 - Chapter 3 Installation guidelines
 - Chapter 4 DAS Software Configuration
 - Chapter 5 Commissioning
 - Chapter 6 RF Commissioning
 - Chapter 7 Model Identification
 
FiberDistributedAntennaSystem(FiberDAS)
95
System Commissioning
Pre-requisites
 EstablishEthernetconnectionbetweentheBGWandallcards
 Powerupallequipment
 EnsureIPaddresseshavebeenassigned
Cardswillbri
eflyflashgreen.SolidgreenindicateswaitingforIPassignment
 VerifyremoteunitfibersareconnectedtocorrectFOIports
 Setnamesforallcomponentsandaddcomponentstothesystem‐See“NamingComponents”section
 ConnectBTStotheBIUensuringproperattenuationfortheBIUcardbeingused
Commissioning Process
1. Oncethefiberisconnectedandverified,turnFOIRFpoweron.
Connectonlyonefibe
rportatatimeandcompletenamingofremote.Otherwise,asecondpersonwillbe
neededattheremotestoidentifytheremotewhen“LocateMe”isenabled.Thiscanbeeliminatedwithgood
projectmanagementandlabelingduringtheinstallationprocess.
Figure 108  
FOI 
RF
Control
FOI RF On
2. Enabletheappropriateopticalportsonthe4‐portFOI
Onlyenabletheoptic
alportsthatarebeingused.Otherwise,thesystemwillalarmwithlowopticallevelson
theunusedports.










