The Elevator Contractor shall provide all labor, tools and equipment necessary for on-site ob-
servations, testing, retesting, inspections and re-inspections as may be required to satisfy the
Code testing requirements, the requirements
of
the local testing authority and the requirements
of
the Owner.
C.
Upon satisfactory completion
of
required tests, the Elevator Contractor shall obtain and submit
to the Owner the Certificate
of
Operation
or
other instrument, which may be required to legally
permit the Owner to operate the elevator.
1.21
FINAL
CLEAN-UP
A. Upon completion
of
the project, the Elevator Contractor shall clean out and remove all loose
materials from the hoistway, pit and machine room; remove all crating and packing materials
and all unused elevator equipment from the job site; clean the machine room floor
of
dirt, oil,
grease and dust and paint the machine room floor, pit and car top
to
provide for the machine
room pit and car top to be dust free at the time
of
the Final Acceptance
of
the elevator system.
1.22
INSTRUCTIONS
TO OWNER
A. The Elevator Contractor shall provide a minimum
of
four (4) hours
of
instructions to the
Owner's personnel upon completion
of
the elevator installation. Instructions shall include
safety procedures, proper operation
of
all equipment and routine maintenance procedures. In
addition, the Elevator Contractor shall provide explanation and demonstration
of
each control
feature and operation, including Independent Service Operation, Emergency Recall Operation,
Phase I and Emergency in Car Operation Phase
II,
and Emergency Power Operation.
1.23
WARRANTY
AND
GUARANTEE
A. The Elevator Contractor shall warrant and guarantee all equipment provided and installed under
this Contract/Specification against defects in materials and workmanship and will correct any
defects not due to ordinary wear and tear or improper use
or
care which may develop within
one (1) year from the date the last elevator is completed, placed into operation and accepted
by
the Owner. This warranty is not intended to supplement normal maintenance service and shall
not be construed to mean that the Elevator Contractor shall provide free service or periodic ex-
amination, lubrication,
or
adjustment due
to
normal use, beyond that included in the Con-
tract/Specifications, nor shall the Elevator Contractor correct, without charge, breakage, malad-
justments, or other trouble arising from abuse, misuse, improper or inadequate maintenance, or
any other causes beyond his control.
1.24
MAINTENANCE
SERVICE
A. Interim Maintenance: The Elevator Contractor shall provide a lump sum price to provide full
coverage maintenance service to
two (2) passenger elevators commencing upon Notice to Pro-
ceed for the modernization contract work. This initial maintenance service shall provide com-
prehensive full coverage maintenance,
as
outlined in the attached maintenance agreement, on
the existing elevator equipment and on each modernized elevator as they are placed back into
operation including emergency callback service and shall be made available on a 24-hour 7 day
per week basis, upon the Owner's request. The service shall continue through until the comple-
tion
of
the modernization contract work and acceptance
of
the last elevator by the Owner. The
amount
of
this lump sum price shall be paid monthly over the schedule provided in the contract
documents. Should the Elevator Contractor finish the project in less time then allotted
by
the
schedule, the Elevator Contractor will be paid for the remaining lump sum amount. Should the
Elevator Consulting and Design, Inc.