Specifications
Governor's .Park Condominium 777 Washington Street
Denver,
CO
4.01
A.
b. Ensure smooth quite operation in full travel, floor-to-floor runs and door operation.
WIRING
All wiring shall be new to ensure proper operation as set forth in this Contract/Specification.
Some hoistway duct may be reused upon prior Consultant's approval.
B.
Provide three (1) Co-Axial Cables and four (4) sets
of
shielded cable in Traveling Cables, to be
terminated at the top
of
the car junction box and at a point inside the elevator machine room or
first floor landing. These wires shall be for Owner's use at a later date. Provide 10% spare for
other wires. Provide wires for new card reader system to be installed on all cars.
5.01 MISCELLANEOUS WORK
AND
SCHEDULE
A. This Contract/Specification covers all work as specifically set forth to bring the elevator sys-
tem up to acceptable standards. Any additional work deemed necessary shall be brought to the
Owner's attention in writing ten (10) days prior to bid date.
B. All work shall be performed during regular working hours
of
regular working days as is cus-
tomary in the elevator industry.
.C. Only one (1) elevator shall be out
of
service at
anyone
time in the performance
of
the work as
specified.
D.
Prior to commencing work, a work schedule shall be submitted to the Owner for approval.
E.
The Elevator Contractor shall confirm power, floor designation, emergency recall floors and
dispatch floor locations, etc., prior to fabricating equipment.
F. All material for all elevators must be onsite or stored in a local warehouse before cars are re-
moved from service for this work. Owner
or
owners' representative will inventory material
prior to start
of
job.
No
exceptions to this item will be granted.
G. The Elevator Contractor shall provide all information, including necessary architectural and
engineering information, required by the Owner to coordinate the design and interface work
of
other trades impacting the elevator work.
H.
• Remove Car
#1
for Modernization
• Com lete Punch List
• Remove Car #2 for Modernization
• Com lete Punch List
• Total Duration Phase
II
Total Project Duration:
3 weeks
1 weeks
14 weeks
1 week
19 weeks
12
weeks
1 week
12 weeks
1 week
26 weeks
45 weeks
Elevator Consulting
and
Design,
Inc.
27