Specifications

Governor's
Park
Condominium
777 Washington Street
Denver,
CO
tractor. All work shall be made absolutely stable and secure and the Elevator Contractor shall
be
held strictly responsible for any damage resulting from failure to properly furnish such sup-
port.
D.
The Elevator Contractor shall protect Owner's property, equipment and stored materials against
damage, dust and dirt at all times and shall confine all methods
of
construction to promote
safety and reduce noise and dust, due to occupancy
of
the property and provide necessary pro-
tective guards, barricades, tarpaulins and drop cloths.
E. The Elevator Contractor shall remove all unused and demolished equipment and rubbish on a
continual basis and shall keep the premises clean at all times during the term
of
the project. At
the completion
of
work, the Elevator Contractor shall leave the premises clean and in such con-
dition as is satisfactory to Owner.
1.15
A.
MATERIAL
AND
EQUIPMENTDELIVERY,
STORAGE
All materials shall be delivered in the original unopened protective packaging and shall be
stored in the protective packaging to prevent soiling, physical damage and wetting.
B.
Equipment and exposed finishes shall be protected during transportation, erection and construc-
tion against damage and stains.
C.
The Elevator Contractor shall confine his apparatus and the storage
of
materials to limits estab-
lished by law, ordinances, permits
or
directions
of
the Owner and shall not unreasonably en-
cumber the premises with his materials. All flammable or combustible materials shall be prop-
erly stored to eliminate potential fire hazards.
1.16
A.
1.17
A.
PROJECT
MANAGEMENT
AND
SUPERVISION
The Elevator Contractor shall designate an experienced Project Manager to perform the admin-
istrative management
of
the project and place a competent Superintendent in charge
of
the pro-
ject throughout the course
of
the work. The Elevator Contractor's on-site job Foreman shall be
responsible for day-to-day operations and scheduling with the Owner. The Project Manager
and Superintendent shall be available to the Owner to assist in the progress and coordination
of
the work
of
the project and shall represent the Elevator Contractor in all matters relating to the
project.
SAFETY
PLAN
The Elevator Contractor shall submit a detailed safety plan for this project at time
of
shop
drawing submittal. Safety Plan shall detail the type and construction
of
the barricades to be
used at open hoistways, rigging to
be
worn by Elevator Contractors, and first aide kit. The su-
perintendent shall hold a safety meeting on site monthly.
1.18
EXECUTION
A.
The Elevator Contractor shall perform the following as part
of
the execution
of
the work
of
the
Elevator Contract:
1.
Comply with all requirements
of
the local Fire Codes that are applicable to this work.
Elevator
Consulting
and
Design,
Inc.
7