PRIOR TO INSTALLATION
Inspect product for any issues before
installing. (breakage, surface defects,
foreign objects, color inconsistency or
color correctness)
Do not install questionable product.
Report any problems you may have to
your dealer BEFORE installing.
STORAGE
It is important to properly store all Diamond
Kote
®
products for protection.
Store siding at on a dry, clean and well
supported surface. Protect material from
direct exposure to weather.
Do not store directly on the ground.
Diamond Kote
®
4-Packs and 2-Packs
are not waterproof. All products must be
kept dry and covered at all times.
Product may come in long, heavy
sections, which requires proper handling.
Carry shrinkwrapped bundles to
desired location before opening to
avoid damaging the painted surface.
Don't carry in a at position.
Pick up product from the center to avoid
marring the surface of items below.
Only carry multiple pieces of siding:
face-to-face or back-to-back.
Do not slide pre-nished siding material
across each other.
Support the product when you cut large
pieces.
Sealed product could become saturated
if not protected during storage.
If the product becomes saturated, do not
install until it dries out completely.
GENERAL GUIDELINES
**Note: DO NOT USE STAPLES.
Minimum 6" clearance must be maintained
between siding and nish grade.
Siding applied adjacent to porches,
patios, walks, roof lines, etc. must have a
1" clearance above any surface.
3/8" clearance should be left between
siding and horizontal ashings.
All exposed wood substrate must be
primed and painted to prevent moisture
intrusion and water buildup.
Best practice for blind or exposed nailing
is to use only 316 stainless steel nails
within 15 miles of the seacoast. Beyond
15 miles, either 304 stainless steel or
hot-dipped galvanized is acceptable.
See Alternate Fastening Options for
fastening lap siding to SIP, ICF and Steel
Frame assemblies.
(PG 10)
Adequate drying time must be allowed
prior to enclosing the wall cavity when
using wet blown cellulose insulation.
With wet blown cellulose insulation, the
insulation must not be in direct contact
with the siding and it will need time to
dry, a minimum of 24 hours or longer if
specied by the insulation manufacturer.
Diamond Kote
®
Building Products should
be cut in a manner to avoid marring the
nished face.
It is recommended to face the board up
when using a combination blade power
miter saw.
Do NOT force or spring siding into place.
Where siding butts window trim, door
casing, masonry, etc., leave a 3/16" gap
and caulk. DO NOT caulk butt joints.
Seal all gaps with a paintable sealant
that meets ASTM-C92
0 Specication,
it is recommended to use DAP SpecLine
92
0.
Use drip-cap ashing above all
horizontal trim to ensure a weather-
tight installation. 1" drip cap is available
in all Diamond Kote colors.
STORE UNDERCOVER
PROPER HANDLING