2.6 Applying Power
Use the following procedure to apply power:
1. Verify that the on/off switch on each ac power entry controller is set to the off
(0) position.
2. Verify that all power cables are attached to the appropriate power supply
StorageWorks building blocks (SBBs).
3. Verify that all external cables are attached to the controller.
4. Make sure that all SBBs are seated firmly in their shelves.
5. Connect the power cord to an ac power entry controller.
6. Connect each power cord plug to a wall outlet receptacle.
7. Apply power to the enclosure by setting the on/off switch on each ac power
entry controller to the on ( |) position.
8. Verify the power is on by checking the light emitting diodes (LEDs) on the
power supply SBBs, environmental monitor unit (EMU), and controller.
These LEDs should be displayed as follows:
• Power supply SBBs—both LEDs (green) are on
• EMU—SYSTEM OK (green) is on
• Controller—reset (green) is flashing
• SW300 cabinet—System OK (green) is on
For further information on SBB LEDs, see Chapter 4.
Note
For further information on controller LEDs and configuration, see the
StorageWorks Array Controllers HS Family of Array Controllers User’s
Guide.
9. Configure the controllers.
Note
For information concerning storage device configuration, see the
StorageWorks Solutions Shelf and SBB User’s Guide.
10. Configure the storage devices.
Unpacking and Installation Instructions 2–5