10 System health check/maintenance
Heat pump:
Is the fan clear from debris?
Is the tray clear from debris?
Is the condensate drain clear from debris?
Is the evaporator coil clean?
Are all of the outer panels secure?
Electrical:
Is the power cable firmly fixed?
Is the earth wire connection secure?
Is the supply voltage correct?
Hydraulics:
Is the system sufficiently pressurized?
Are there any leaks in the system?
Is the filter clear of debris?
NOTE: It is recommended that the strainer is checked and cleaned 24 hours after
commissioning, and regularly within the first weeks of operation.
Indoor settings:
Are the set temperatures and heating times suitable for the occupants?
Is the building warm enough for the occupants or does the heating curve need to be adjusted?
Is the UI screen working correctly?