Specifications

TM 11-5820-670-30
2-4. TEST METER TESTS.
PURPOSE
The test meter tests provide an overall performance check of the radio set. Test switch S9801 selects
various operating voltages in the receiver-transmitter and applies them to test meter M9601.
TEST EQUIPMENT AND MATERIALS
Power Supply PP-2953/U
Maintenance Kit MK-1035/ARC-131
All cables ore part of MK-1035/ARC
TEST SETUP
Connect equipment as shown in test setup diagram. Turn on all equipment and allow at least 5 minutes
for warmup.
EL1AT140
INITIAL EQUIPMENT CONTROL SETTINGS
Set equipment controls as indicated in the following table.
CONTROL AND SWITCH SETTINGS
EQUIPMENT
RT-8231ARC-131
CONTROL OR SWITCH
TEST SWITCH
XMTR HI-LO
POSITION/SETTING
Set as instructed in
procedures.
HI
2-4