5•Service
Doc. 065289-03 10/12 113
7. Connect the cable from the new leak sensor (P/N 058053) to the Dionex ICS-
1100 cable.
8. Feed the cables back inside the Dionex ICS-1100. Align the leak sensor with
the component panel opening and fingertighten the screw.
9. Make sure the leak sensor does not touch the bottom of the drip tray.
5.16 Priming the Pump
1. Verify that the eluent reservoir is filled, the reservoir cap is installed and hand
tightened, and the liquid line from the Dionex ICS-1100 to the reservoir cap is
connected.
2. Verify that the waste lines are directed to a waste container.
3. The priming procedure consists of two parts:
Priming the eluent lines with a syringe (see Section 5.16.1). Perform this
procedure at initial installation, after changing eluents, or when eluent
lines are empty.
Priming the pump heads with the Prime button (see Section 5.16.2).
Perform this procedure after the eluent lines are primed.
5.16.1 Priming the Eluent Lines with a Syringe
NOTE Prime the eluent lines after initial installation, after
changing eluents, or when eluent lines are empty.
1. Verify that the pump is turned off.
2. Connect a 10 mL syringe (P/N 079803) to the priming valve port on
the primary pump head (see Figure 5-23
).