Operation Overview - 46 JT922 Operator’s Manual
Planning
CMW
Planning
1. Gather information about jobsite. See page 51.
2. Inspect jobsite. See page 52.
3. Classify jobsite. See page 54.
4. Plan bore path. See page 57.
5. Check supplies and prepare equipment. See page 63.
6. Load equipment. See page 70.
Setting Up at Jobsite
1. Prepare jobsite. See page 62.
2. Unload drilling unit from trailer. See page 73.
3. Position drilling unit and frame. See page 77.
4. Assemble strike system. See page 95.
5. Anchor drilling unit. See page 93.
6. Calibrate tracker with beacon that will be installed in beacon housing. See tracker operator’s manual.
Drilling
1. Start system. See page 77.
2. Prime drilling fluid pump. See page 77.
3. Engage tracker control if desired. See page 106.
4. Assemble drill string. See page 80.
5. Drill first pipe. See page 82.
6. Record bore path. See page 85.
7. Add pipe. See page 83.
8. Drill remaining pipes in pipe box.
Correct direction. See page 84.
9. Surface drill head. See page 86.