2.2 High Voltage Terminal Connection
Remove the
3 locknuts
inside the
electronic
box to swing
box open.
• Route incoming AC power wire through the high voltage conduit and run wire in the operator electronic box as shown.
• Be sure wiring is installed in accordance with local codes. Be sure to color code all wiring.
• It is recommended that a surge suppressor be installed on the high voltage power lines to help protect the operator
and circuit board from surges and power fluctuations.
• Dual operators (Primary/Secondary) require AC power to EACH operator.
High
Voltage
Input Wire
DANGER
HIGH VOLTAGE!
DO NOT power up and cycle the operator until the
“DIP-Switches” and the “Limit Switches” have been
adjusted. Damage could occur to the gate and operator.
1
2
3
AC Power AC Power
Dual Operators
Electronic Box
CAUTION
High Voltage AC input power
MUST MATCH the operator
specifications or DAMAGE will
occur and VOID the warranty!
A separate power disconnect switch may
be needed in your area. Check local
building codes before installation.
Recommended by DoorKing.
External Power
Disconnect Switch
208/230 VAC
SINGLE Phase
Chassis
Ground
High Voltage
AC Input Wire
Hot
115 VAC Output
Hot
Use only two legs of the
incoming 3-phase power.
208/230/
460 VAC
THREE Phase
Chassis
Ground
High Voltage
AC Input Wire
Hot
115 VAC Output
Hot Hot
Check polarity of
three phase motor.