Example 1:
A time discount is to apply Monday to Friday from 10:00 p.m. to
06:00 a.m. Furthermore, time discount is to apply all day during
week-ends. Three period settings are required to define this
combination of time discounts:
Example 2:
A time discount is to apply Saturdays and Sundays between 10:00
a.m. and 2:00 p.m. Separate periods must be defined for each of
the two days:
Period 1
Set start day ALL=7 Set start time 22:00
Set end day ALL=7 Set end time 23:59
Result: Time discount is given between 10:00 p.m. and midnight of the same
day.
Period 2
Set start day ALL=7 Set start time 00:00
Set end day ALL=7 Set end time 06:00
Result:Time discount is given between midnight and 06:00 a.m. of the same
day.
Period 3
Set start day Sa=5 Set start time 06:00
Set end day Su=6 Set end time 23:59
Result: Time discount is given continuously all through the week-end.
Period 1
Set start day Sa=5 Set start time 10:00
Set end day Sa=5 Set end time 14:00
Period 2
Set start day Su=6 Set start time 10:00
Set end day Su=6 Set end time 14:00
Result: Time discount is given on Saturdays and Sundays between 10:00 a.m.
and 2:00 p.m.
Non example:
Period 1
Set start day All=7 Set start time 22:00
Set end day All=7 Set end time 06:00
Result: No time discount will be given as the end time cannot be earlier than the
start time for the same ‘day’ or ‘ALL’. In this case a time discount up till midnight
and another one from midnight and onwards should have been defined. (See