Instructions / Assembly
DRI8DG: SMARTWALL
®
Detailed Installation
Faster, More Convenient and Better Results. DRICORE SMARTWALL®
PATENTED MODULAR WALL SYSTEM
4
3. From your list of materials, take your roll of
polyethylene and measure off a manageable length,
6’ to 8’ usually, and cut it into 14” wide strips. Then
carefully tape the length of one edge of the poly
leaving ½” of tape exposed. Tape this piece at the
very top of the DRICORE SMARTWALL panel. Using
a pair of scissors cut the poly along the bottom of
each floor joist so it can fold up into the cavity. Fold
the poly up into each floor joist cavity.
4. Re-tape the new piece of poly in the cavity to
the sides of the floor joists and bottom of the floor
sheathing ensuring no open area’s for air leakage
(see photo below).
Installing a window box extension in
your DRICORE SMARTWALL system:
As you are installing your DRICORE SMARTWALL
panels you will eventually come to a basement
window. The window is already installed in the
concrete or block, so what you need to do is cut an
opening in the DRICORE SMARTWALL panels to
allow for the installation of a window box
extension. First, determine the dimensions and
locations of the window box required. The window
box will basically be the same size as the existing
window frame. Let’s say the window frame we are
extending is 24” high x 30” wide (outside of the
jamb to outside of the jamb). You will be building a
window box out of finished grade plywood that is
this same dimension. Now you are ready to mark
the DRICORE SMARTWALL opening on the surface
of the panels. Add an additional 1” to the height and
width to allow for a little adjusting. Also add 1¼” to
the dimension of your opening to allow for the
rough frame you will need to install in the opening.
Therefore you will be cutting an opening in the
DRICORE SMARTWALL panels 26¼” x 32¼”. Make
sure this opening is roughly centered with the
actual window (you have 1” of play, the 1” we added
for adjusting). Cut your opening in the DRICORE
SMARTWALL panels and install the panels as normal
(see photos on right). You are now ready to build
the rough frame from the 5/8” plywood and install
it. Measure the distance from the surface of the
drywall to the front side of the existing window
jamb. Check this dimension at all 4 corners of the
window, they should be the same. If your basement
window was not installed plumb by the builder (this
sometimes happens) adjust your window jamb
extension pieces accordingly. Install the rough
frame the same way as a door opening rough
frame, and then install your window box, adjusting
it to line up with the existing window jamb and
fastening into place using 2 ½” screws or nails.
Vapour Barrier Tie In:
You will need to tie your existing vapour barrier
in your joist cavities to your DRICORE
SMARTWALL vapour barrier (the drywall skin of
DRICORE SMARTWALL will require priming
with a vapour barrier rated primer) to ensure
continuity of the vapour barrier system. To do
so, follow the steps listed below.
1. Remove any vapour barrier tape that may
already be in place at the joist cavities. Then pull the
existing polyethylene barrier down and away from
the flooring cavity (it should now be hanging over
the face of the DRICORE SMARTWALL.
2. Add 4” (or whatever is required) of insulation
in the cavity to bring the insulation even to the
surface of the DRICORE SMARTWALL drywall skin,
and then fold the poly you pulled down back up
into place. Do not staple or tape this.