Specifications

Page 28 • DRI-STEEM CRUV Electric Humidifier Installation, Operation, and Maintenance Manual
Start-up checklist
LW series controller
Tap/softened water
Adjust humidistat setting to create a call for humidity.
Open shut-off valve on water supply line, and confirm that
drain valve is closed. Tank should begin filling with water
through fill valve.
Shortly before fill valve shuts off, rising water level causes water
to come in contact with the bottom probe, and heating element
contactor(s) will be actuated.
Check heater cut-off circuit as follows:
1. Close manual water supply valve, then open drain valve and
start draining tank.
2. When water level drops below bottom probe, the heating
element contactor(s) drop out.
3. When Step 2 above has completed, close drain valve.
Check function of field-installed safety controls, such as fan
proving switch. Contactor(s) should drop out when proving
switch is open.
Check heater draw by testing and recording voltage and
amperage in each phase. Readings should match humidifier
name plate readings (name plate is on humidifier housing).
Inspect installation for steam or air leaks while operating
humidifier. Seal any leaks.
DI/RO water option
Adjust humidistat setting to create a call for humidity.
Open shut-off valve on water supply line, and confirm that
drain valve is closed. Tank should begin filling with water
through fill valve.
Shortly before fill valve shuts off, float-operated heater cut-off
switch will “make,” and heating element contactor(s) will be
actuated. A time delay relay circuit prevents contactor chatter
that would otherwise occur due to bouncing of heater cut-off
float.
Check heater cut-off circuit as follows:
1. Close manual water supply valve, then open drain valve and
start draining tank.
2. When water level drops past switching level on heater cut-off
float, the heating element contactor(s) drop out.
3. When Step 2 above has completed, close drain valve.
Check function of field-installed safety controls, such as fan
proving switch. Contactor(s) should drop out when proving
switch is open.
Check heater draw by testing and recording voltage and
amperage in each phase. Readings should match humidifier
name plate readings (name plate is on humidifier housing).
Inspect installation for steam or air leaks while operating
humidifier. Seal any leaks.
Operation