9.6.Test Procedure
9.6.1.Air Discharge:
This test is done on a non-conductive surfaces. The round discharge tip of the discharge
electrode shall be approached as fast as possible to touch the EUT.
After each discharge, the discharge electrode shall be removed from the EUT.
The generator is then re-triggered for a new single discharge and repeated 10 times
for each pre-selected test point. This procedure shall be repeated until all the air discharge
completed.
9.6.2.Contact Discharge:
All the procedure shall be same as Section 9.6.1. except that the tip of the discharge electrode
shall touch the EUT before the discharge switch is operated.
9.6.3.Indirect discharge for horizontal coupling plane
At least 20 single discharges shall be applied to the horizontal coupling plane, at points on
each side of the EUT. The discharge electrode positions vertically at a distance of 0.1m from
the EUT and with the discharge electrode touching the coupling plane.
9.6.4.Indirect discharge for vertical coupling plane
At least 20 single discharge shall be applied to the center of one vertical edge of the coupling
plane. The coupling plane, of dimensions 0.5m X 0.5m, is placed parallel to, and positioned
at a distance of 0.1m from the EUT. Discharges shall be applied to the coupling plane, with
this plane in sufficient different positions that the four faces of the EUT are completely
illuminated.
9.7.Test Results
PASS.