Installation Guide
10
illustrates the two-story building. In the case 
of the two-story installation, the base of the 
Firestop Radiation Shield is nailed to the top 
of the framing, with the pan (the depressed 
portion of the base), facing downwards. For 
the multi-story installation, the base is nailed to 
the bottom of the framing with the pan facing 
upwards. The cylindrical component of the 
Firestop Radiation Shield is then slipped down  
through the base from the top until it rest on 
the bead.  (Figure 9). Refer to Table 2 for the  
framing requirements.
7. Assemble Chimney Sections: Lower 
and seat the female end of the rst Chimney 
Section in the Support Box. (Figure 11). It 
will twist-lock onto the male end of a Low 
Prole Starter Section, which is a component 
of the Support Box. Turn Pipe Sections 
clockwise, rmly to lock them together. Sheet 
metal screws may be used to reinforce the 
connection, however they are not normally 
required. Screws are only acceptable in the 
outer liner. 
8. Install Attic Insulation Shield:  Install 
the Attic Insulation Shield where the chimney 
passes into an attic. It’s purpose is to prevent 
debris and insulation from getting too close to 
the chimney. (Figure 12).  An installed Attic 
Insulation Shield is 14 inches high. In attic 
areas where this shield won’t t, a Square 
Support Box, (which is available in heights 
up to 36 inches), can be used instead of an 
Attic Insulation Shield, provided it reaches 
through the roof; refer to the Roof Supported 
Installation section on page 14.  If the 
chimney is fully enclosed through the attic, 
an Insulation Shield is not required, however, 
again, Ventilated Flashing must be used. 
Where the chimney passes into the attic, 
install the Attic Insulation Shield as follows: 
a. If the Firestop Radiation Shield extends 
above the attic oor, no modications are 
Figure 9
FRAMING
NAILS (AT LEAST 2 PER SIDE)
FIRESTOP RADIATION SHIELD SDP-FRS
NAILS (AT 
LEAST 
2 PER 
SIDE)
FRAMING
FIRESTOP RADIATION 
SHIELD SDP-FRS
Figure 10
Figure 11
VENTILATED FLASHING
CHIMNEY SECTION
SDP-P
SUPPORT BOX
SDP-S, SDP-RS, SDP-SB
MULTI-STORY GOING 
INTO NEXT FLOOR
TWO-STORY GOING 
INTO ATTIC