Specifications

PROPRIETARY DATA: This document contains proprietary data of ABB Inc. No disclosure, distribution (electronic or otherwise),
or other means of dissemination may be made without written permission.
3BUS 208 000 R1301 61Utility Service Installation
SP Power Up Procedure
The following power up sequence is required to ensure no wiring errors or
malfunctioning equipment cause a failure that could jeopardize a successful
installation.
1. Verify power is tagged off and locked out at the Motor Control Center (MCC).
2. Verify all circuit breakers in the SP and the SPDC are turned off (see Figure 4-4).
Figure 4-4 Circuit Breakers
3. Install all required wiring. The connection terminals for the main supply to the
SP are located behind the cover over the main circuit breaker. The phase
conductors terminate directly to the main circuit breaker; neutral and ground
to the adjacent terminals.
4. Remove all debris from the installation work and vacuum the enclosure. Verify
no tools or assembly material were left in the equipment.
Head Split Switch