INSTALLATION SETUP
Eaton 9170
+
UPS (3–18 kVA) User's Guide S 164201393 Rev E www.eaton.com/powerquality
16
6. Select the position for the UPS in the equipment rack.
7. Select the proper holes in the rail that position the UPS at the
desired location in the rack.
8. With one person lifting each side of the UPS cabinet, carefully slide
the UPS into the equipment rack until the rack-mount ears of the
cabinet are flush with the front vertical rails of the rack. Verify that
the holes in the ears align with the holes in the rack.
9. Secure the UPS in the rack using eight 10-32
1/2 Torx
®
screws
(16 for 6-slot cabinets) or other appropriate customer-specified
screws.
Floor Anchor Kit Installation
An optional floor anchor kit (ASY-0548) is available for all sizes of the
Eaton 9170+ UPS. The kit helps to stabilize the UPS or battery cabinet in
the event of accidental bumps or small floor movements. Any testing to
specific seismic requirements is the responsibility of the customer.
The floor anchor brackets, shipped separately from the UPS and battery
cabinet, should be attached inside the lower front and rear edges of the
cabinet before installing power and battery modules and before making
connections to the intended power source.
Use mounting hardware supplied with the floor anchor kit to attach the
brackets to the UPS or external battery cabinet (see Figure 11). The
customer is responsible for specifying and supplying floor mounting
bolts.
Mounting Centers for 8 mm (5/16”) Floor Bolts
Dimension (see Figure 11) Measurement
A 36.8 cm (14.5)
B (3- and 6-slot cabinets) 76.8 cm (30.25)
B (9- and 12-slot cabinets) 87 cm (34.25)