UPS INSTALLATION PLAN AND UNPACKING
Eaton
®
9390 UPS (20–80 kVA) and 9390IT (20-40 kVA) Installation and Operation Manual S 164201603 Rev 4 www.eaton.com/powerquality
3-3
Battery
Compartment
Shipping Pallet
Figure 3‐2. Eaton 9390IT UPS (20-40 kVA) as Shipped on Pallet
W A R N I N G
The UPS cabinet is heavy (see Table A or Table B on page A-4). If unpacking instructions are not closely
followed, the cabinet may tip and cause serious injury.
C A U T I O N
S Do not install a damaged cabinet. Report any damage to the carrier and contact your Eaton service
representative immediately.
S Do not tilt the UPS cabinet more than 10° sideways from vertical or the cabinet may tip over.
To unpack the cabinet:
1. Carefully inspect the outer packaging for evidence of damage during transit.
2. Use a forklift or pallet jack to move the packaged cabinet to the installation site,
or as close as possible, before unpacking. Insert the forklift or pallet jack forks
between the pallet skids.
NOTE Verify that the forklift or pallet jack is rated to handle the weight of the cabinet (see Table A or
Table B on page A-4 for cabinet weight).
3. Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft)
on each side for removing the cabinet from the pallet.
NOTE The UPS cabinet is shipped with a debris shield covering the ventilation grill on top of the UPS. Do
not remove the debris shield until installation is complete.
4. Remove the protective covering from the cabinet.
5. Remove the packing material, and discard or recycle in a responsible manner.