14  Installation for the Street Lighting Solution 
Step 1: Install the Segment Controller 
Configure the Segment Controller (see Chapter 3, Setting Up the Segment 
Controller, on page 23) and install it at any convenient location for the street 
lighting solution. For example, you can install it on one of the street light poles 
or utility poles (typically below the neutral space) within the area for the street 
lighting solution. Ensure that the Segment Controller has power.  
Place the Segment Controller into Acquisition Mode; see Automatically 
Discovering Devices on page 27. While in Acquisition Mode, the Segment 
Controller continually attempts to discover devices (luminaires and CRD 3000 
Street Light Bridge modules) on the power line network. In Acquisition Mode, 
the Segment Controller’s Service LED flashes at 4 Hz. 
As the Segment Controller establishes communications with each luminaire and 
commissions it, the Segment Controller turns the lamp off.
5
Note that if you install luminaires first, all of the lamps within the network stay 
on until you install the Segment Controller. Some installations might require 
several days of installation time, so some of the lamps could remain on for one or 
more days. 
Recommendation: For installations in which the luminaires are managed by 
monitoring software (such as Streetlight.Vision Data Collect) and have group 
switching established, install the Segment Controller during the day so that the 
schedule defined by the monitoring software can specify the luminaire’s behavior 
(that is, the schedule should specify that lamps are off during the day) as the 
Segment Controller establishes communications with each luminaire. Thus, you 
can receive visual confirmation that the Segment Controller has established 
communications with each luminaire.  
When all of the lamps are off, the installation is complete. For any that do not 
turn off, proceed to Step 3 to install CRD 3000 Street Light Bridge modules; the 
Segment Controller will discover and commission the installed luminaires 
through the CRD 3000 Street Light Bridge modules. 
Step 2: Install Luminaires 
Install one or more luminaires. Each luminaire’s lamp should turn on to indicate 
that it has power.  
Allow the Segment Controller to discover and commission each installed 
luminaire. If you install the luminaires before the Segment Controller, record 
each luminaire’s physical location and Neuron ID so that you can enter this 
information into the Segment Controller Device Web page for each luminaire. 
For example, record the luminaire’s GPS coordinates, pole ID, or map grid 
reference. 
If you install the Segment Controller before any of the luminaires, the Segment 
Controller will discover and commission each luminaire as it is installed. If a 
given lamp does not turn off within approximately two minutes, you should 
5
 This behavior is defined by the luminaire’s LonMark
®
 interoperable profile. The Segment 
Controller updates the primary data point for the luminaire during device commissioning; for a 
luminaire’s LonMark profile, the primary data point is the on/off snvt_switch network variable. 