Operating Instructions and Installation Instructions

[
ECTIVE
®
SINUS/SINE INVERTER – CSI-/SSI-SERIES
]
51
Commissioning of the inverter
1. Make sure that the on/off button of the inverter is switched “off”. If the input
voltage is provided by a supply unit, switch it off as well.
2. Connect the inverter to the DC voltage source with the delivered cables.
3. Connect the delivered power cable to the inverter (only for inverters with charger)
4. Switch on the inverter.
5. wait approx. 12 sec. until the inverter turns on.
6. Switch on all of the electronic devices one by one.
Please note!
Sparking!
The connection process to the input DC voltage source leads to sparking because of
the charging of the internal capacitors.