Installation guidelines 
To ensure correct operation, install the duct detector using the 
following guidelines: 
•  Install the duct smoke detector on a flat section of HVAC 
duct between six and ten duct widths from any bends or 
obstructions. 
•  Install supply-side detectors at a point downstream from 
the supply fan and after the air filter. 
•  Install return-side detectors at a point before the return air 
stream is diluted by outside air. 
Verify the duct air velocity 
In order to verify airflow direction and velocity, air must be 
moving through the HVAC system. 
To verify the duct air velocity: 
1.  Drill a small hole at the point where the duct smoke 
detector is being installed. 
2.  Using the SD-VTK Air Velocity Test Kit and a suitable air 
velocity meter, verify that the air velocity in the HVAC duct 
falls within the specified operating range of the detector 
and note which direction the air flows.  
3.  If the air velocity does not fall within the specified range, 
relocate the detector and seal the hole in the HVAC duct. 
Refer to Technical Bulletin P/N 3101212 for additional 
information pertaining to installation locations. 
Select the appropriate sampling tube: 
•  Select a sampling tube that extends at least two-thirds 
across the width of the duct. 
•  For duct widths greater than 36 inches, use a sampling 
tube that is longer than the width of the duct. 
•  Sampling tubes are available in the following lengths: 
Model
  Description 
SD
-T8   8-inch sampling tube 
SD
-T18   18-inch sampling tube 
SD
-T24  24-inch sampling tube 
SD
-T36   36-inch sampling tube 
SD
-T42  48-inch sampling tube 
SD
-T60  60-inch sampling tube 
SD
-T78  78-inch sampling tube 
SD
-T120  120-inch sampling tube 
To assemble the detector: 
1.  Assemble the duct smoke detector as shown in Figure 2. 
2.  Rotate the air sampling tube so the inlet holes face the 
direction of airflow. 
3.  The sampling tube is normally installed from the rear, but it 
can also be installed from the front of the detector as 
shown in Figure 3. This method requires that you remove 
the detector cover. 
Figure 2: Duct detector assembly 
Detector
Sampling tube
socket
Exhaust tube
Thick
gasket
Thin
gasket
Exhaust tube
socket
Coupling
Sampling tube
(ordered separately)
Plug
Figure 3: Sampling tube installation 
Sampling tube
connector
Sampling tube
(fully assembled)
Detector
To install the detector: 
1.  Attach the drill template to the HVAC duct at desired 
mounting location. 
2.  Drill (or punch) the mounting holes where indicated. 
Note: Sampling tubes longer than 36 inches must be 
supported at both ends of the duct. 
3.  If using an air sampling tube that is longer than the width 
of the duct, drill a 3/4-inch hole on the opposite side of the 
duct for tube to pass through. 
4.  Remove any rough edges from the holes. 