Installation Guide and Manual

17
START-UP PROCESS
Plumbing installation checklist must be filled out and left with water heater. Must flush water heater for 2 minutes at a minimum.
Eemax installation checklist and start-up procedure for ProSeries XTP water heaters
Important - Read and fully understand all steps outlined below before proceeding. Failure to do so may damage the water heater and
void any warranty. Technical support is available at 1 (800) 543-6163
Plumbing installation checklist
Step
Category
Action
Confirmed by
Notes
1
Water
Heater is supplied with clean potable water
2
Water
Plumbing orientation is correct water connections on the bottom - inlet on the right,
outlet on the left
3
Water
Ensure piping connections are not causing stress or torque on the inlet and outlet
fittings
4
Water
No leaks at water connection or in plumbing network
5
Water
Water pressure is between 40-90 PSI (min 35psi)
6
Water
Long pipe runs, high flow rates and valves closing can cause pressure spikes (water
hammer) above 1000 PSI. Consult piping schematic to ensure arrestors and regulators
are properly sized and located.
7
Water
(with power off) Open supply valves to water heater - run water through fixtures to
purge all air and debris in system. With water flowing, visually inspect the clear
element tubes between the inlet and outlet manifold to ensure no air bubbles are
present. (this may take several minutes)
8
Water
Using a flashlight, visually inspect heating chamber for any signs of leakage
9
Water
Ensure Water Heater will not freeze
10
Water
Ensure all local plumbing codes are met
11
Water
Plumbing installation correct and complete
Important - Read and fully understand all steps outlined below before proceeding. Failure to do so may damage the water heater and
void any warranty. Technical support is available at 1 (800) 543-6163
Electrical installation checklist
Step
Category
Action
Confirmed by
Notes
12
Power
(with power off) - Breaker and disconnect are of proper size and correctly installed
13
Power
(with power off) - Wiring and conduit are of proper size and correctly installed.
14
Power
(with power off) - Wiring connections at terminals are correct orientation, tight, with
no stray wire strands or pinched sheathing
15
Power
(with power off) - Proper ground,(not neutral) is clean, and tight
16
Power
(no water flowing, do not turn it on, close outlet water shut off valve if uncontrolled
environment-left hand side) Apply power - ensure voltage and phasing is according
to model rating
17
Power
Disengage power after voltage and phasing is confirmed (open outlet shutoff valve if
closed during step 14)
18
Power
Ensure all local electrical codes are met
19
Power
Electrical Installation correct and complete