Installation Instructions User guide
Table Of Contents
- Table Of Contents
- Section 1: General Notes And Guidelines
- Section 2 - Parts Identification
- Section 3 - Static Starter Sill Preparation and Installation
- Section 4 - Dynamic Starter Sill Preparation and Installation
- Section 5 - Dynamic Starter Sill Anchor Installation
- Section 6 - Intermediate Floor Slab Anchor Installation
- Section 7 - Unit Inspection and Preparation for Installation
- Section 8 - Setting Units at Static Starter Sills
- Section 9 - Setting Units at Dynamic Starter Sills
- Section 10 - Setting Typical Intermediate Units
- Section 11 - Setting Assembled (One Piece) Corner Units
- Section 12 - Applying Critical Seals
- Section 13 - Applying Typical Perimeter Seals
- Section 14 - Deglaze / Re-glaze Procedures - Captured System
- Section 15 - Deglaze / Re-glaze Procedures - SSG System
EFCO 2009 Page 16
Series 8700 / 8800 Unitized Curtain Wall Installation Instructions
30. As the starter sill sections are anchored into the final position, slide the gutter base anchors into position. The base anchor is flush with the end
of the starter sill at the jambs, centered on the vertical at intermediate verticals, and flush with the mitered ends of the starter sill at corner
conditions.
31. Finish installing all starter sill sections as previously described until the installation is completed.
Section 3 - Static Starter Sill Preparation and Installation
FM02 - 8” Base Anchor
FM01 - 7” Base Anchor
FM02 - 8” Base Anchor
FM01 - 7” Base Anchor
FM28 - 8” Base Anchor
FM22 - 7” Base Anchor FM29 - 8” Base Anchor
FM23 - 7” Base Anchor
FM26 - 8” Base Anchor
FM24 - 7” Base Anchor
FM27 - 8” Base Anchor
FM25 - 7” Base Anchor
Figure 21
Static Starter Sill
FM02 - 8” Base Anchor
FM01 - 7” Base Anchor