Series 8700 / 8800 Unitized Curtain Wall Installation Instructions
Figure 49
Figure 47
Section 5 - Dynamic Starter Sill Anchor Installation
1. Assemble the starter sill anchors by attaching the anchor bar to the starter sill anchor (17C6) with (6) SFP9 fasteners. Offset anchors may be required at
jamb conditions. Anchors may come to the field preassembled, depending on project requirements. Refer to the final approved shop drawings for anchor
configurations, bolt sizes and other project specific information.
2. Set anchors into the opening, inserting anchor bolts into the slots in the approximate locations required. Do not use shims between the starter sill anchor and
the condition. If in certain situations due to field tolerance issues shims are used, they must be full bearing shims. The shims must fully support the entire
load bearing surface of the anchor. Should this condition occur, the project structural engineer should be consulted.
FM04 Anchor Bar
(8” system shown)
or FM03 Anchor Bar
(7” system)
17C6 Starter Sill
Anchor with
bituminous coating
Anchor bolts as
required.
Figure 48
Figure 50
Jamb Anchor
Intermediate Anchor
(6) SFP9
Block-out in slab as
required for anchor.
Insert anchoring
system in slab
as required.
Jamb Starter Sill
Anchor Assembly
Intermediate Starter
Sill Anchor
17D3 Serrated
Washers