30. Set the unit to the required elevation height and level it by turning the jack bolt at each mullion anchor clockwise to raise, or counterclockwise to lower the unit
in to the final position.
31. Match drill the slab anchors through the hook anchors on both sides of the unit, and install the pinning screws to lock the frame unit into the final position.
See Figures 95 and 96.
32. Repeat steps 5 through 31 until all units on the dynamic starter sill level have been installed.
33. When erecting a long run of units, check overall frame location dimensions at every fifth unit to avoid dimensional buildup and to ensure that units are
properly positioned with regard to established bench marks.
34. Proceed to “Section 10 - Setting Typical Intermediate Units”.
Section 9 - Setting Units at Dynamic Starter Sills
Figure 96 Figure 95
Hook Anchor
17D4 Slab
Anchor
Dead Load Anchor
Once the units are set and final
adjustments are made, turn the
washer so that the serrations
align and secure anchor bolts.
17D3 Serrated
Washers
17D3 Serrated
Washers
Hook Anchor
Dead Load Anchor
Once the units are set and final
adjustments are made, turn the
washer so that the serrations
align and secure anchor bolts.
17D4 Slab
Anchor
Once final adjustments have been
made, match drill the hook anchor
and install the pin screw to lock the
lateral position of the frame unit.
Once final adjustments have been
made, match drill the hook anchor
and install the pin screw to lock the
lateral position of the frame unit.