- Section 8 - Setting Units at Static Starter Sills
- Section 9 - Setting Units at Dynamic Starter Sills
- Section 10 - Setting Typical Intermediate Units
- Section 11 - Setting Assembled (One Piece) Corner Units
- Section 12 - Applying Critical Seals
- Section 13 - Applying Typical Perimeter Seals
- Section 14 - Deglaze / Re-glaze Procedures - Captured System
- Section 15 - Deglaze / Re-glaze Procedures - SSG System
EFCO 2009 Page 64
Series 8700 / 8800 Unitized Curtain Wall Installation Instructions
1. The deglaze and re-glaze procedure must be performed from a swing stage or man lift from the exterior of the building. Follow the sealant manufacture’s
sealant application instruction for deglazing and re-glazing. When deglazing an opening or openings at a structural silicone glazed unit follow these
instructions:
a. Cut and remove the weather seal, side blocks and setting blocks, from around the lite of glazing.
b. Using tools, such as automotive deglazing tools, cut though the glazing sealant removing glazing, old gasket and sealant from the opening. Some
areas may be accessible from the interior.
c. Cut away the sealant from the substrate, leaving a thin film (approximately 1/32” thick) of sealant on the frame. Do not damage the surface finish of
the substrate. Alternatively, if the remaining sealant exhibits adhesive failure, completely remove all sealant, but take care not to damage the
substrate finish.
d. Remove all remaining gasket pieces or sealant residue from inside the gasket reglets.
Section 15 - Deglaze / Re-glaze Procedures - SSG System
Figure 141
Cut completely
through the sealant
joint and remove the
sealant and gaskets.
Cut out and remove
the weather seals.
Remove setting
and side blocks
from the opening of
lite to be deglazed.
Cut out and remove
the weather seals.
Cut completely
through the sealant
joint and remove the
sealant and gaskets.
Cut out and remove
the weather seals.
Figure 142