reboot
3.4. LibraPlus Field Installation
This section discusses how to install, configure and test a LibraPlus in the field.
Before you can install LibraPlus equipment in the field:
All units should be configured as described in the Configuration section
Site preparation work must be complete
Ensure all necessary tools and equipment are available
3.4.1. Site Preparation
Site preparation involves checking actual customer site conditions and ensuring that the site is ready
for LibraPlus installation. Each site is unique, however the following guidelines are provided.
1. Obtain a customer site plan or make a site plan. This document should describe where to place the
LibraPlus unit, what kind of equipment to use, and the required configuration settings of the unit.
2. Cables should always be connected without exceeding their recommended bend radius.
3. Ensure that there is enough room for ventilation.
4. Confirm that AC power and Ethernet access are available.
5. Inspect the recommended LibraPlus location to determine the following:
the mounting structure is suitable;
LOS and Fresnel Zone clearances can be met, because of OFDMs superior Non Line of Sight
performance these requirements will not be as stringent as for other systems;
location of the LibraPlus is acceptable.
6. Check cable routes and entry and exit points to ensure that they are practical.
3.4.2. Tools and equipment
You will require the following tools and equipment
Standard tool kit
Test equipment
Drill and bits
LibraPlus Unit
Weatherproofing materials
LibraPlus mounting hardware
Ladder
Cables: Outdoor CAT-5 Cable, AC power cable.