Additional Applications
Furnace variable speed blower – (Figure 12) a
fifth wire connection will be needed to speed up
the gas furnace blower for air conditioning and
HeatChoice electric heating operation. Add the
fifth wire to the gas furnace “Y” terminal as
shown on the diagram.
Note: Connection wires shown are in addition to
4-wire thermostat and 4 wires to furnace.
Note: In the latest version of the HeatChoice,
external jumper wires are no longer needed to
ramp up the blower for air conditioning and
HeatChoice electic heating.
AUX Load Control, other Electro products – on HeatChoice control board, bottom right, connect blues (from
other product) to COM and EL. (Note: this is a true function from the blue wires, it does not follow the override
switch).
2-stage or variable burner gas – most furnaces ignore or do not take W2 (or Ruud “V”) action unless there is
an input to W1. This means you can take a wire directly from 2-stage heat roomstat W2 to the furnace W2 and
until the system is switched over to standby with the HeatChoice control board activating W1 there should be no
furnace action.
2-speed or 2-stage air conditioning – load control
action may be required with the outdoor unit Y2. This
can be accomplished by routing the roomstat Y2
through a relay contact (onboard tabs) and the outdoor
unit Y2.
- Roomstat Y2 – COM
- EL – outdoor unit Y2
Wood furnace – inlet air sensor required, must order
and install EM5713 sensor for all non-automatic
standby applications. The heated air coming off of the
wood furnace must be less than about 90° before the
electric elements will activate. Install the EM5713 in
series with the load management control blue wire
(Figure 13).
Large mass furnace heat exchanger, oil, etc. – if there was an active standby heat call during the release of a
load control back to electric, the heat build-up within the heat exchanger and the heating up of electric elements
may initially produce an output temperature which exceeds the manual reset (250°). Normal tubular gas furnace
heat exchanger should not be a problem because the electric element initial temperature delay is approximately 3
minutes. By removing the XD jumper on the HeatChoice control board, a two minute delay is added between
each stage 2, 4, and 5. This will help reduce the chances of experiencing nuisance tripping of the manual reset
limit switch.
Fi
g
ure 12
Fi
g
ure 13