INSTALLATION REQUIREMENTS
This section explain how to install and configure the transmitter for your location All internal switching and
setup should be done by qualified service person.
PARAMETER REQUIREMENTS
TRANSMITTER
ROOM
The room should be clean and free of dust. The building floor
shuold be able to support a load capacity >1000kg/m
2
INSTALLATION
AREA
The transmitter should be installed to have space around enough
for ventilation and for maintenance actions to be allowed.
The minimun requirement space is one meter outer boundary of
transmitter.
TEMPERATURE
The transmitter is designed to work from -5° up to 45°C, anyway
to ensure long life is better to keep the room temperature lower
than 35°C.
ELECTRICAL
PLANT
The transmitter power consumption is <10.2kVA (13.45kVA in
analog mode), we suggest to design the main power line
capacity increased by at least more than 50%.
MAINS SYSTEM
The mains system should be three phase with neutral. The
trasmitter is available in two different mains voltage models for
380VAC and 230VAC system.
AIR COOLING
The outlet air should be convoyed out of the room by suitable ducts
(the transmitter air output adapters has a diameter of 320mm).
The air flow required is 2500m
3
/h.
ANTENNA
The transmitter RF output interface is EIA 1+5/8” (others interface
can be supplied on request in order to match the antenna feeder
or combiner input). The RETURN LOSS of the system should be
greater than 27dB in the operation channel.
Note: the standard cooling system is supplied with internal ventilation system, air inlet and outlet are
on the top. Other different installations can be proposed for various air connection arrangements.