Installation Instructions
WATER-RESISTANT LAMINATE FLOORING
1102_2019 | Page 1
Site and Material Preparation
A) Remove carpet and padding. Also remove any wood ooring installed on concrete. Do not remove products unless they are asbestos-free.
B) Undercut door frame and wallbase. Slide the ooring at least
1
/4″ underneath the door frame and wallbase. Also leave a concealed
3
/8” minimum expansion
space under each.
C) Remove bumps or peaks in suboor and ll depressions with oor leveling compound to ensure no more than
3
/16″ unevenness per 10-foot span.
D) Acclimate unopened product before installation. If there is no time for acclimation, there should be no more than a difference of 25° F and 20% relative
humidity between the stocking/transportation environment of the ooring and the nal installation environment of the ooring.
E) Clean debris from suboor before installation.
F) For concrete suboors, install vapor barrier with overlapped seams of 8″ or more.
G) For planks without attached underlayment, install over single layer of underlayment appropriate for laminate oors.
Job Site
Site Requirements
Laminate is a durable oor covering, not intended as structural material.
Laminate requires a clean, dry, secure suboor that meets building codes.
The following requirements are not intended to supersede federal, state or local
building codes, but as with many other interior nish products, may require
modifying existing structural components for successful installation. Owner
assumes responsibility for compliance with all building codes.
Laminate oor is suitable for use in climate controlled (35-65% RH and 60-85°
F) indoor installations only and should not be installed over any oor with a sump
pump or in a room with a oor drain. Laminate oor can be installed above, on or
below grade.
A moisture test is strongly recommended to determine if high moisture exists in the suboor.
When using a calcium chloride moisture test for concrete suboors (ASTM F1869), values
must be ≤ 5 lbs/1000ft²/24-hr or <80% RH with an in situ probe (ASTM F2170). Moisture
readings of wood suboors must be ≤ 12%.
Acceptable job site conditions, including relative humidity and suboor moisture conditions,
must be maintained throughout the lifetime of the ooring. Laminate ooring is installed as
a oating oor and requires the use of T-moldings in doorways 4 ft (1.22 m) or less and in
rooms 40 feet (12.2 m) or larger in length or width. Floor movement must not be constrained
by glue, nails, screws, hardware or other xed obstructions. This product must be installed in
accordance with these installation instructions.
10' (3 m)
> 5" (130 mm)
6 mil (0.15 mm) virgin PE vapor barrier
ground
> 8" (200 mm)
>8 po
E
suboor
> 8" (200 mm)
6 mil (0.15 mm) virgin
polyethelene vapor barrier
F
G
%
48 hours 60° – 85° F 35% – 65% RH
D
C
A
Door Frame
Wallbase
Casing
1″
(2,5 cm)
B
Cutting Line
Site and Material Preparation
Installation Instructions