User's Manual

Installation
37 SOLA HD
®
S5KC
equipment changes, while the UPS is still providing power. Follow these steps to properly and safely
add or change the optional PODs.
1. Ensure that the POD breaker is in the Off position.
2. Using a Phillips screwdriver, remove the two screws that are at the top of the POD cover plate
and retain these for reattaching the POD.
3. Remove the POD cover plate to expose the POD connectors.
4. Insert the bottom of the POD into the slot provided, and then connect the POD connectors.
5. Secure the POD by using the two screws removed in Step 2.
6. Repeat Steps 1 through 5 to install a second POD on the SolaHD S5KC (only the 16-bay frame
has two POD ports).
7. Connect the equipment to the appropriate outlets.
8. Close the POD breaker(s) to connect AC power to the outlets.
9. After commissioning the UPS, turn On the connected equipment per the manufacturer’s
instructions (see 2.5.6 - Commissioning/Startup Procedures).
2.5.6 Commissioning/Startup Procedures
The SolaHD S5KC can be commissioned with or without AC power being connected. Follow these
steps for the initial UPS system startup:
Checks Before Commissioning/Startup
___ 1. Verify that the AC power connections are wired properly and all connections are tight.
___ 2. If using external battery cabinets or third-party battery systems, verify that the DC power
and communication cables are connected properly and all connections are tight.
___ 3. Measure and record the AC input voltage and frequency. This will be needed to properly
configure the output voltage of the SolaHD S5KC system.
___ 4. If any modules within the SolaHD S5KC system were removed during installation, verify that all
modules are fully inserted and that the module locking levers are in the locked position.
___ 5. If the UPS is being connected into a Remote Emergency Power Off (REPO) circuit, refer to
3.3 - REPO (Remote Emergency Power Off) for the REPO connection details and
instructions. If no REPO circuit is required or used, the factory-installed jumper must be
removed from the terminal block Pins 9-10 as described in 3.2 - Dry Contact Ports.
___ 6. Verify that the UPS internal bypass breaker is in the open position with the guard in place
and secure.
NOTE
This is the breaker located near the POD port.
NOTE
The connector should connect only one way, matching the color of the pins.
NOTE
Distribution PODs PD2-101, PD2-102, PD2-103, PD2-104, PD2-105, PD2-106 and PD2-107
should not be used if the UPS output voltage is set to 220/127V.
NOTE
When connecting distribution POD’s to an S5KCC or S5KCD frame, the L-L output receptacles
will connect to the 240V taps of the output transformer, not to the 208V tap. Verify receptacle
voltage and load ratings before energizing the load.