TROUBLE POSSIBLE CAUSE CORRECTIVE ACTION
A) Automatic switch activated
Reset the automatic switch; check the cause
for the activation
11. The compressor does
not work
B) Compressor internal heat protection
activated
Check the compressor winding resistance
; after
reset, check the tension and the electric absorption;
check the working parameters are in the nominal
range of values
C) The contactor does not work Check the contacts and the contactor coil
Check the thermostatic valve overheating is correct;
12. The compressor is noisy
A) Liquid return to the compressor check the valve bulb is properly placed, fixed and
insulated
B) The compressor is damaged Replace the compressor
13. Probe alarm
A) The probe corresponding to the alarm
code is defective or disconnected
Check the probe connection and if it works; in case of
defect, replace it.
5.6 Routine maintenance
5.6.1 Type and frequency of periodical checks
Before acceding any component inside the unit, turn the main switch of the power supply to OFF position.
Then, also turn the unit main switch to OFF position.
Only trained technicians are alllowed to perform operations with powered electrical panel and with
open panel board, since some functions of the system fail.
It is recommended to carry out periodical checks in order to make sure the unit works properly. Only authorized and
skilled technicians are allowed to perform this kind of operations, included any maintenance operation.
5.6.2 Operations on the cooling circuit
Every time an operation involves the cooling circuit discharge, the gas must be collected by means of the appropriate
gas recovery for environmental safety reasons.
Once the repair on the cooling circuit is performed, carry out the following operations:
Ø
Leak detection;
Ø
Vacuum and dehydratation;
Ø
Refrigerant charge.
A) LEAK DETECTION
Charge the cooling circuit with the gasous refrigerant up to reach a pressure of 1 bar. Then, add anhydrous nitrogen by
means of cylinders with reducer up to reach a pressure of 15 bar.
Look for possible leakage and, if present, discharge the cooling circuit before welding (with phosphorus copper
alloy with a minimum of 2% of silver).
Discharge completely the cooling circuit before welding in order to avoid explosions.
Do not use oxigen instead of nitrogen in order to avoid explosions.