Enphase IQ8 Install and Operation Manual

IQ8 / IQ8+ / IQ8M / IQ8A / IQ8H Micro Installation and Operation
12 © 2022 Enphase Energy Inc. All rights reserved. Aug 2022
Parts and Tools Required
In addition to the microinverters, PV modules, and racking, you will need the following:
Enphase Equipment
Enphase IQ Gateway: Required to monitor production. IQ Gateway (model ENV-IQ-AM1-240)
communications gateway or IQ Combiner (model X-IQ-AM1-240-B, X-IQ-AM1-240-2, X-IQ-
AM1-240-3, X-IQ-AM1-240-3C).
Enphase Installer App: Download the Enphase Installer app, open it, and log in to your
Enphase Installer Platform account. Use it later to scan microinverter serial numbers and
connect to the IQ Gateway to track system installation progress. To download, go to
enphase.com/installerapp or scan the QR code at right.
Tie wraps or IQ Cable Clips (Q-CLIP-100)
Enphase Sealing Caps (Q-SEAL-10) for any unused drops on the Enphase IQ Cable
Enphase Terminator (Q-TERM-10) typically two needed per branch circuit
Enphase Disconnect Tool (Q-DISC-10)
Enphase Field Wireable Connectors (male and female: Q-CONN-10M and Q-CONN-10F)
Enphase IQ Cable:
Cable Model
Connector Spacing
PV Module
Orientation
Connector Count
per box
Q-12-10-240
1.3m
Portrait
240
Q-12-17-240
2.0m
Landscape(60-cell)
240
Q-12-20-200
2.3m
Landscape(72-cell)
200
Other Items
• AC junction box
• Number 2 and 3 screwdrivers
• Wire cutters, voltmeter
• Torque wrench, sockets, wrenches for mounting hardware