Enphase IQ8 Install and Operation Manual

IQ8 / IQ8+ / IQ8M / IQ8A / IQ8H Micro Installation and Operation
22 © 2022 Enphase Energy Inc. All rights reserved. Aug 2022
Method 2: Use Enphase Installer App to Clear the Condition
On the list of detected microinverters, a green dot or red square appears to the left of each microinverter serial
number. A green dot indicates Status OK. A red square indicates an event for that microinverter.
Tap the to the left of the serial number to view details for a microinverter event.
If the microinverter status shows that there is an active DC Resistance Low Power Off
condition, tap the to send the clear message to the affected microinverter. The
app then indicates that a clear message was sent.
Other Faults
All other faults are reported to the Gateway. Refer to the Enphase IQ Gateway Installation and Operation
Manual at enphase.com/support for troubleshooting procedures.
Troubleshoot an Inoperable Microinverter
To troubleshoot an inoperable microinverter, follow the steps in the order shown
WARNING: Risk of electric shock. Always de-energize the AC branch circuit before servicing. Never
disconnect the DC connectors under load.
WARNING: The Enphase Microinverters are powered by DC power from the PV modules. Make sure you
disconnect the DC connections and reconnect DC power and then watch for the solid green about six
seconds after connection to DC power.
A. Make sure AC breakers and disconnects are closed.
B. Check the connection to the utility grid and verify that the utility voltage is within allowable ranges.
C. Verify that AC line voltages at all solar power circuit breakers at the load center and subpanels are within the
ranges shown in the following table.
D. Verify that AC line voltage at the junction box for each AC branch circuit is within the ranges shown in the
following table:
240 Volt AC, Single Phase
L1 to L2
211 to 264 VAC
L1, L2 to ground
106 to 132 VAC
208 Volt AC, Single Phase
L1 to L2
183 to 229 VAC
L1, L2 to ground
106 to 132 VAC