RSD switch Additional Info
Installer Memo - North America     
1  © 2022 Enphase Energy Inc. All rights reserved.  May 13, 2022 
Wiring The Rapid Shutdown Switch to IQ System Controller 2 
Overview 
The  Enphase  rapid  shutdown  switch/Enphase  system  shutdown  switch  (EP200G-NA-02-
RSD)  provides  Rapid  Shutdown  (RSD)  capability,  as  required  by  NEC  standard,  for  IQ8 
Microinverters when used with IQ System Controller 2 (EP200G101-M240US01). The Rapid 
Shutdown Switch and IQ System Controller 2 are certified to the UL1741 Photovoltaic Rapid 
Shutdown Equipment (PVRSE) requirement. 
This special bulletin includes instructions to enable installers to avoid issues with the rapid 
shutdown switch wiring and installation. The bulletin covers: 
1.  When to use the RSD switch with IQ System Controller 2 (EP200G101-M240US01)? 
The RSD switch is required and must only be used for IQ8 microinverters. Refer to page 2 of 
this  bulletin  on  how  to  use  IQ  System  Controller  2  with  legacy  microinverters  (IQ6/7  or 
M215/250) 
2.  How to safely wire the RSD switch to the IQ System Controller 2? 
Installers MUST ensure that the IQ System Controller 2 is powered off before performing any 
wiring. Wiring an energized IQ System Controller 2 is a safety hazard. If the RSD terminals 
are inadvertently connected to any other conductive surface while the IQ System Controller 2 
is energized the IQ System Controller 2 can be damaged and will require replacement. 
Installers must follow the wiring scheme as described in this document. The wiring scheme for 
the Rapid Shutdown Switch depicted in the installation guide is incorrect for a small number 
of IQ System Controller 2 units manufactured prior to December 8, 2021. Incorrect wiring 
prevents  IQ  System  Controller  2  from  exiting  the  rapid  shutdown  state  and  from  being 
commissioned correctly. The installation guides with incorrect wiring scheme have a revision 
of 140-00236-02 or lower. 
It is recommended that installers remove the terminal block from System Controller before 
wiring the jumpers/ cable headers. 
3.  How to energize IQ System Controller 2 and exit Rapid Shutdown?  
Installer must keep the Rapid Shutdown (RSD) switch turned off before energizing the IQ 
System Controller 2. If the RSD switch is turned on before energizing the IQ System Controller 
2, the IQ System Controller 2 goes into manual override mode, which forces installers to follow 
the process to remove the IQ System Controller from manual override mode and leads to 
delays during commissioning. 